A $250,000 permit was filed for an H5 Data Center screen wall near 1625 Rockwell Avenue. The description says adjacent buildings along Emerald Court would be demolished to expand the generator yard, with the new wall intended to preserve the street-facing storefront character along St. Clair.
H5 Data Center Screen Wall H5 Data Center has acquired adjacent buildings along Emerald Court and will demolish those buildings to expand their generator yard. They are proposing to construct a new screen wall along Saint Clair Avenue that will maintain the characteristics of the storefronts of the buildings to be demolished.